Manually launching business processes

You can launch BPs manually by selecting an activity and choosing Edit > Linked Business Process > Start. To manually launch BPs, these conditions must be met:

Manual launch under various conditions:

Auto-control on Schedule Sheet Properties

Auto-update Activity Status on Activity

System Behavior

On/Off

Checked

Manually launched BP is tracked by the system, and actuals will be auto-populated on launch and completion.

On/Off

Unchecked

Scope Management will not keep track of BP completion and auto-population of actual start and finish dates of manually launched BP.