Scope Management functionality can be enabled on any schedule sheet (including master schedule sheets). You can modify the properties associated with scope management. These include:
- Auto-control
- Schedule start date
- Error notification to users and groups
To manage scope management properties
- In User Mode, navigate to the project or shell Schedule Manager and select Schedule Log. The Schedule Sheets log opens.
- Select a schedule sheet and click Properties.
- On the General tab, complete or modify the fields described in the following table and then click OK.
In this field: | Do this: |
---|---|
Auto-control | Controls the automatic update of tasks. The default is Off. Setting auto-control to On enables the automatic launch of BP records. Setting auto-control to Off means that BPs will not be launched automatically on activities and completion conditions will not be checked on activities. Users can still launch BPs manually. Note: Unifier disregards predecessor/successor dependency relationships when you manually start an activity, even if auto-control is set to On in the schedule sheet properties. |
Schedule Start Date | Drives the dates of floating activities on the schedule sheet. Activities cannot begin before this date, unless their preceding activities complete previous to this date. |
Notify users and/or groups on errors | Select users and groups to be notified if there are errors during the scope management task routing. |