% Earned Calculation Method option is Update Activity and all resources on activity start and finish

If the entry method and option settings on the Budget and Progress Method Setup window are:

then this data entry method scenario results:

Activity or Resource

Data Element

Data Entry Method

Activity

 

Activity % Complete

Calculated (Weighted Hours) and (read-only).

{Sum of [ (Resource Progress Quantity / Resource Quantity) * (Resource Quantity)] / Sum of (Resource Quantity) } * 100

Only hard booked resources will be considered.

Earned Progress

Calculated (Weighted Cost)

{Sum of [ (Resource Earned Progress / Resource Quantity) * (Resource Amount)] / Sum of (Resource Amount) } * 100

Resource

 

Progress Quantity

Manual entry

Earned Progress

Calculated based Update Activity and all resources on activity start and finish.

For example: If % earned on Actual Start = 5% and % earned on Actual Finish = 95 % then,

When Actual Start is entered, Earned Progress = 5% * Quantity

When Actual Finish is entered, Earned Progress = 100% * Quantity.