If the entry method and option settings on the Budget and Progress Method Setup window are:
- % Complete and Earned Progress entry method = Independently Control % complete and earned quantity
- % Complete Calculation Method option = Resource updates Activity - weighted avg. of resource costs
- % Earned Calculation Method option = Manual activity % earned - updates resource % earned
then this data entry method scenario results:
Activity or Resource | Data Element | Data Entry Method | ||
---|---|---|---|---|
Activity | ||||
| Activity % Complete | Calculated (Weighted Hours) and read-only. {Sum of [ (Resource Progress Quantity / Resource Quantity) * (Resource Amount)] / Sum of (Resource Amount) } * 100 All booked resources will be considered. | ||
Earned Progress | Manual entry | |||
Resource | ||||
| Progress Quantity | Manual entry | ||
Earned Progress | Calculated (Activity-level Earned Progress * Quantity) |