If the entry method and option settings on the Budget and Progress Method Setup window are:
- % Complete and Earned Progress entry method = Independently Control % complete and earned quantity
- % Complete Calculation Method option = Resource updates Activity - weighted avg. of resource costs
- % Earned Calculation Method option = Update Activity and all resource on activity start and finish
then this data entry method scenario results:
Activity or Resource | Data Element | Data Entry Method | ||
---|---|---|---|---|
Activity | ||||
| Activity % Complete | Calculated (Weighted Hours) and read-only. {Sum of [ (Resource Progress Quantity / Resource Quantity) * (Resource Amount)] / Sum of (Resource Amount) } * 100 All resources will be considered. | ||
Earned Progress | Calculated (read-only) based Update Activity and all resources on activity start and finish. For example: If % earned on Actual Start = 5% and % earned on Actual Finish = 95 % then, When Actual Start is entered, Earned Progress = 5% When Actual Finish is entered, Earned Progress = 100% | |||
Resource | ||||
| Progress Quantity | Manual entry | ||
Earned Progress | Calculated (read-only) based Update Activity and all resources on activity start and finish. For example: If % earned on Actual Start = 5% and % earned on Actual Finish = 95 % then, When Actual Start is entered, Earned Progress = 5% * Quantity When Actual Finish is entered, Earned Progress = 100% * Quantity. |