If the entry method and option settings on the Budget and Progress Method Setup window are:
- % Complete and Earned Progress entry method = Activity and resource % complete updates % earned
- % Complete Calculation Method option = Lead resource updates Activity and other resources
- % Earned Calculation Method option = Lead resource updates Activity and other resources
then this data entry method scenario results:
Activity or Resource | Data Element | Data Entry Method |
---|---|---|
Activity | ||
| Activity % Complete | Calculated (Weighted Hours) and read-only. {Sum of [ (Resource Progress Quantity / Resource Quantity) * (Resource Amount)] / Sum of (Resource Amount) } * 100 All resources will be considered |
Earned Progress | Calculated (read-only) Same as Activity % Complete | |
Resource | ||
| Progress Quantity | Manual entry. (Only resource that is selected under drop-down). For all other resources, Progress Quantity will be calculated based on (Leader Progress Quantity / Leader Quantity) * Resource Quantity |
Earned Progress | Calculated (read-only) Same as Progress Quantity |