% Complete Calculation Method options are not available

If the entry method and option settings on the Budget and Progress Method Setup window are:

then this data entry method scenario results:

Activity or Resource

Data Element

Data Entry Method

Activity

 

Activity % Complete

Calculated (read-only)

Same as Earned Progress

Earned Progress

Calculated (Weighted Hours) and read-only.

{Sum of [ (Resource Earned Progress / Resource Quantity) * (Resource Amount)] / Sum of (Resource Amount) } * 100

All resources will be considered

Resource

 

Progress Quantity

Calculated (read-only)

Same as Earned Progress

Earned Progress

Manual entry