If the entry method and option settings on the Budget and Progress Method Setup window are:
- % Complete and Earned Progress entry method = Activity and resource % earned updates % complete
- % Complete Calculation Method option = Not available
- % Earned Calculation Method option = Lead resource updates Activity and other resources
then this data entry method scenario results:
Activity or Resource | Data Element | Data Entry Method | |||
---|---|---|---|---|---|
Activity | Activity % Complete | Calculated (read-only) Same as Earned Progress | |||
Earned Progress | Calculated (Weighted Hours) and read-only. {Sum of [ (Resource Earned Progress / Resource Quantity) * (Resource Amount)] / Sum of (Resource Amount) } * 100 | ||||
Resource | |||||
| Progress Quantity | Calculated (read-only) Same as Earned Progress | |||
| Earned Progress | Manual Entry (Only resource that is selected under drop-down). | |||
For all other resources, Earned Progress will be calculated based on(Leader Earned Progress / Leader Quantity) * Resource Quantity | |||||
| |||||
|