The option "Enable P6 sources" is not available in a Cost Sheet created in a Standard Project or Standard Project Template.
The cost sheet that has the option "Enable P6 sources" selected is not included when you want to create a new Cost Sheet by copying a cost sheet.
The template that has the option "Enable P6 sources" selected is not included when you want to create a new Cost Sheet using: New > Cost Sheet > Copy from Template.