If the user clicks on Update > Linked Schedule Sheets, then only the Activity Data will get updated on the destination (linked) Schedule Sheets from the template, and not the sheet properties.
- If Auto-scheduling is enabled in the Linked (destination) Schedule Sheet, then after the Activity Dates update through Update> Linked Schedule Sheets, the re-scheduling will take place.
- If Auto-scheduling is disabled in the Linked (destination) Schedule Sheet, then only the Activity Dates is updated and no re-scheduling occurs. That is to state that the change will be reflected in dependent activities.
When auto-scheduling is disabled, if you push dates to the Master Schedule Sheet from Program Activity Sheet, then you can update changes for a particular activity, but there will be no impact of your changes reflected in dependent activities. Also, since the Master Schedule Sheet is updated by Program Activity Sheet, a Refresh icon appears in the log, next to the title.