Activity Sheet Permissions in the System Activity Sheet Permissions Tab

Note: If the user gets any of the permissions below, then the user can access the Activity Sheet node, in the User mode.

To enable the users create, modify, and view the activity sheets, where the user can manually create project schedules, go to the shell, Admin mode and from the left-hand Navigator click Access Control node to open the Access Control window.

In the Access Control window, the following Activity Sheet permissions will appear in the System Activity Sheet Permissions tab:

Before 21.4 Upgrade

After 21.4 Upgrade

Full Access

At module-level:

  • Send System Activity Sheet Data
  • Get System Activity Sheet Date
  • View

At sheet-level:

  • Modify
  • All
  • Modify
  • Current
  • View

Send Data

At module-level:

  • Send System Activity Sheet Data

Get Data - All

At module-level:

  • Get System Activity Sheet Data

Get Data -Current

At module-level:

  • Get System Activity Sheet Data

Modify -All

At module-level:

  • Modify
  • All

Modify - Current

At module-level:

  • View

At sheet-level:

  • Modify
  • Current

View - All

At module-level:

  • View

At sheet-level:

  • View
  • All

View - Current

At module-level:

  • View

At sheet-level:

  • View
  • Current

See Also

Setting up the Schedule Manager

Additional Options for Setting Up the Schedule Manager

Importing an Activity Attribute Form

Create Schedule Sheet Templates

Deleting Schedule Sheets

Grant Schedule Manager and Custom Calendar Permissions to Users

Refresh Schedule Sheet Data

Updating Schedule Sheet Properties from Templates

Update Schedule Sheet Activities from Templates

Importing Schedule Files

Scope Management Setup

About Activity-level Editing

Permissions Setting for Activity Sheet

Permissions for the System WBS Sheet