Synchronization

The synchronization of the following two commands (on the OOTB Data Mapping templates) is scheduled to run daily:

Synchronization can be performed:

The Unifier Provider performs a check to see if the Unifier Project is linked to the corresponding P6 Project.

To ensure a successful synchronization, do the following:

  1. Set the Shell attribute DE = uuu_integrated_with to P6.

    Note: If the attribute was missing, after this setup the integration will take place.

  2. Receive the Activity Sheet data from Gateway and:
    • If an "Activity Sheet" does not exist in Unifier, create the "Activity Sheet," populate the fields with the data received, and name the sheet as: <P6 project name>.
    • If an "Activity Sheet" exist in Unifier, update the "Activity Sheet" with the data from Gateway.

You need to perform the steps above to create the "Activity Sheet" within Unifier Shells for the first time, only. Once you create an "Activity Sheet," the hourly synchronization updates the "Activity Sheet" with the latest data received from Gateway.

When projects between Unifier and P6 are linked for the first time, Gateway ensures that a P6 Project attribute that is integrated is checked.

If a "Get Activity Data from " synchronization is performed, but the P6 Project that must correspond to the Unifier Project is not found by Gateway, then Unifier will generate an error-message.

Sending Activity Sheet data to P6

When you synchronize, the Unifier Provider performs the following:

Additional information about synchronization

Connectivity issues with Gateway or incorrect Gateway parameters will cause synchronization to fail. Use History, Admin mode, to see the list of failed synchronizations, if any.

Criteria for successful data exchange

Ensure that the fields ("Update Activity Sheet from P6" and "Send Activity data to P6") in the Data Mapping templates are not overlapping and a field that is set to map from P6 to Unifier is not added to the "Send" template.

Note: The OOTB Data Mapping templates are designed in a way that the fields are exclusive; therefore, when you edit a Data Mapping template, ensure that you keep the fields that are exclusive intact.

If you use DE = uuu_int_p6_project_id for linking P6 and Unifier projects, when the "Project ID" field in P6 is updated, then the "P6 Project ID" (uuu_p6_project_id), field in corresponding Unifier Shell, must be updated manually.