Open a Scenario Sheet (Standard View)

On the Portfolio Manager log, double-click the portfolio that contains the sheet you want to open.

Unifier displays one of these scenario sheets:

You can resize the column that is available in the left of the split. The fields, in the left side of the split, will be editable along with the fields in the right side of the split.

In the Project Portfolio Manager (PPM) scenario sheet, regardless of their position (left or right splits), the following are considered special columns, and read-only:

These fields are read-only because the option “Enable Column Editing” (in the Column Properties window) is not selected.

For the “Start Date” column, if the Project State is in execution, then the column will not be editable in the scenario sheet, whether placed in right or left side of the split.

For the “Start Date” column, if the Project state is not in execution, since the field is editable in the right side of the split, if the column is moved to left it can be edited in that scenario sheet.

The read-only columns will have a background color.

For a selected cell, the corresponding row, and column header, will be highlighted in color, with border.