Duplicate a Scenario (Standard View)

To duplicate a scenario

  1. At the top of the scenario sheet window, select the tab containing the scenario you want to duplicate.
  2. Click Duplicate in the top, right-hand corner of the window.

    Unifier duplicates the scenario into a new tab, which you can rename. All the projects in the original scenario will be duplicated to the new scenario, including their linked or unlinked state, and current column widths, targets, sorting, etc. For the new scenario, Unifier will calculate the new totals and then calculate the variance to show the difference.