The Cost Schedule Index (CSI) reflects the relationship between CPI and SPI. The CSI value should be close to 1.0. The farther the value from 1.0, project or shell recovery becomes more difficult to achieve.
CSI = CPI x SPI
Example: 0.53 x 0.67 = 0.3551