Change Start Dates (Classic View)

You can change the start dates of planned projects, but not those in execution. When you change a start date, Unifier shifts the end date to preserve the project duration, and also shifts the cash flow numbers (excluding pre-actuals) left or right to preserve the cash flow distribution.

To change a start date

  1. Double-click the date in the Start Date column. Unifier displays a calendar.
  2. Choose the new date from the calendar and press the Enter key on your keyboard.

Unifier shifts the end date and the cash flow numbers to reflect the change.

Before date change:

After date change:

How Unifier Distributes Cash Flow

Unifier stores all cash flow amounts by month in the database. The logic Unifier uses to distribute cash flow dollars is rendered in monthly allocations and presented as follows: