This sheet lists the actual time (hours) entered by each resource using time sheet business processes, displaying resource hours for the project/shell or across projects/shells.
You can select the time sheet business process to use.
To view the actuals summary sheet
- In the company-level or project-level Resource Sheets log, select Actuals Summary Sheet and click Open.
- You can view this sheet by hours or cost:
- To view by hours, click the View menu and choose Mode > Hours. The sheet displays the actual hours from time sheets.
- To view data by cost, click the View menu and choose Mode > Currency Amount. The sheet displays the cost charged against each resource from time sheets.
Column | Description |
---|---|
Resource Name | This sheet displays hour and cost information for each resource that has submitted time sheet business processes. |
To define the time sheet to roll up to the actuals sheet
- On the actuals summary sheet, click the Properties button.
- In the Business Process field, click the drop-down list and choose the Timesheet business process to use to roll up.
- Click OK.