Schedule Manager audit log

Each change in the Schedule Manager creates a record in Unifier, which is useful for auditing purposes. An audit report of these records shows detailed information on dates, events, actions, and old values versus new values, along with the user or proxy user who performed the action.

To view schedule sheet details in the audit log

  1. Navigate to the Schedule Sheets log in the Schedule Manager node.
  2. In the View menu, click Audit Log.

    You can review audit log entries for Date, Event, Action, Field, Old Value, New Value, User Name, Proxy User, and Attachments.

To view cell details in the audit log

  1. Navigate to the Schedule Sheets log in the Schedule Manager node and open a schedule sheet.
  2. Under the File menu, click Audit Log.

    You can review audit log entries for Date, Event, Action, Field, Old Value, New Value, User Name, Proxy User, and Attachments.