Update Multiple Activities

You can use the Activity Sheet to update multiple activities at once.

To update multiple activities

  1. In User Mode, navigate to Projects tab > Programs > Schedule Manager > Activity Sheets. The Activity Sheet log opens.
  2. Select the Activity Sheet and click Open.
  3. Modify the data as needed. Cells that are modified are highlighted on the sheet. Only elements that were marked as editable can be modified. To undo changes in a row, select the row and click Refresh.
  4. Click the Save button. The Activity Update Status window opens.

    Activity Update Status window

    You cannot modify the Activity Sheet while the status window is active. The status window scrolls to display In Process projects.

    These are some possible activity update errors:

    • Date (either manually entered or automatically calculated) conflicts with a dependency
    • Date entered is before the scheduled Start Date
  5. Click on the OK button to return to the Activity Sheet.

    There are icons in the first column. The check mark icon displays for successfully processed project rows.

    Successful update of an Activity Sheet

    The X mark icon displays for rows that could not complete the processing due to errors. The X mark icons are hyperlinks. Click the icon to open a dialog box that describes the error encountered by the update process for that specific project row in the update.

Error on update of Activity Sheet

You can modify data elements other than the system defined Start Date, Finish, Date or Duration directly to matching activities without affecting other activities.

If there are Finish-Start dependencies:

Changes to activities that occur through Activity Sheet update are shown on the Audit Log.