For BPs to launch automatically from activities, these conditions must be met:
- Auto-control must be set to On on the Schedule Sheet properties
- Activity is not manually controlled, which means that Auto-update Activity is selected
- Activity has a BP setup
- Activity has the status Not Started
- Activity has no predecessors or the predecessors are all in Complete status
- The Start Date for the activity is not in the future