If the Schedule Attribute form includes an Activity Earned Value Filter field (uuu_activity_ev_filter), you can set up progress filtering for earned value sheets in the Cost Manager.
To set up the schedule sheet for progress filtering
- Open a schedule sheet in a template or project/shell.
- Add the Activity Earned Value Filter data element as a column to the schedule sheet.
- Enter an alphanumeric value, such as "progressable" or "non-progressable," into the column cell. (Use whatever term you like.)
- Save the schedule sheet.