% Earned Calculation Method option is Manual Activity % earned - updates resource % earned

If the entry method and option settings on the Budget and Progress Method Setup window are:

then this data entry method scenario results:

Activity or Resource

Data Element

Data Entry Method

Activity

 

Activity % Complete

Calculated (Weighted Hours) and (read-only).

{Sum of [ (Resource Progress Quantity / Resource Quantity) * (Resource Quantity)] / Sum of (Resource Quantity) } * 100

Only hard booked resources will be considered.

Earned Progress

Manual entry

Resource

 

Progress Quantity

Manual entry

Earned Progress

Calculated

(Activity-level Earned Progress * Quantity)