If the entry method and option settings on the Budget and Progress Method Setup window are:
- % Complete and Earned Progress entry method = Independently Control % complete and earned quantity
- % Complete Calculation Method option = Lead resources updates Activity and other resources.
- % Earned Calculation Method option = Lead resource updates Activity and other resources
then this data entry method scenario results:
Activity or Resource | Data Element | Data Entry Method |
---|---|---|
Activity | ||
| Activity % Complete | Calculated (Weighted Hours) and read-only. {Sum of [ (Resource Progress Quantity / Resource Quantity) * (Resource Amount)] / Sum of (Resource Amount) } * 100 All resources will be considered. |
Earned Progress | Calculated (Weighted Cost) and read-only. {Sum of [ (Resource Earned Progress / Resource Quantity) * (Resource Amount)] / Sum of (Resource Amount) } * 100 | |
Resource | ||
| Progress Quantity | Manual Entry (Only resource that is selected under drop-down). For all other resources, Progress Quantity will be calculated based on (Leader Progress Quantity / Leader Quantity) * Resource Quantity |
Earned Progress | Manual Entry (only resource that is selected under drop-down). For all other resources, Progress Quantity will be calculated based on (Leader Earned Quantity / Leader Quantity) * Resource Quantity |