If the entry method and option settings on the Budget and Progress Method Setup window are:
- % Complete and Earned Progress entry method = Activity and resource % complete updates % earned
- % Complete Calculation Method option = Manual activity % complete and resource % complete
- % Earned Calculation Method option = Not available
then this data entry method scenario results:
Activity or Resource | Data Element | Data Entry Method | ||
---|---|---|---|---|
Activity | ||||
| Activity % Complete | Manual entry | ||
Earned Progress | Calculated (read-only) Same as Activity % Complete | |||
Resource | ||||
| Progress Quantity | Manual entry | ||
Earned Progress | Calculated (read-only) Same as Progress Quantity |