% Earned Calculation Method option is Lead resource updates Activity and other resources

If the entry method and option settings on the Budget and Progress Method Setup window are:

then this data entry method scenario results:

Activity or Resource

Data Element

Data Entry Method

Activity

 

Activity % Complete

Calculated (Weighted Hours) and read-only.

{Sum of [ (Resource Progress Quantity / Resource Quantity) * (Resource Amount)] / Sum of (Resource Amount) } * 100

All resources will be considered

Earned Progress

Calculated (read-only)

Same as Activity % Complete

Resource

 

Progress Quantity

Manual entry. (Only resource that is selected under drop-down). For all other resources, Progress Quantity will be calculated based on

(Leader Progress Quantity / Leader Quantity) * Resource Quantity

Earned Progress

Calculated (read-only)

Same as Progress Quantity