If the entry method and option settings on the Budget and Progress Method Setup window are:
- % Complete and Earned Progress entry method = Activity and resource % earned updates % complete
- % Complete Calculation Method option = Not available
- % Earned Calculation Method option = Manual activity % earned and resource % earned
then this data entry method scenario results:
Activity or Resource | Data Element | Data Entry Method | |
---|---|---|---|
Activity | |||
| Activity % Complete | Calculated (read-only) Same as Earned Progress | |
Earned Progress | Manual entry | ||
Resource | |||
| Progress Quantity | Calculated (read-only) Same as Earned Progress | |
Earned Progress | Manual entry |