% Complete Calculation Method options are not available

If the entry method and option settings on the Budget and Progress Method Setup window are:

then this data entry method scenario results:

Activity or Resource

Data Element

Data Entry Method

Activity

 

Activity % Complete

Calculated (read-only)

Same as Earned Progress

Earned Progress

Manual entry

Resource

 

Progress Quantity

Calculated (read-only)

Same as Earned Progress

Earned Progress

Calculated (read-only)

(Activity-level Earned Progress * Quantity)