Using Graded Approach to Schedule Adherence

Graded approach to schedule adherence is a method for tracking adherence using four distinct levels of work scheduling (A, B, C, and D).

The levels of work scheduling are:

To configure graded schedule adherence:

  1. Ensure you have enabled a project for Work Process:

    The sys_workprocess=WORKWEEK, sys_scope_freeze, and sys_schedule_freeze UDFs are populated and History Level are set to Activity.

  2. Ensure history exists for the project as of the scheduled freeze date and T-0 baseline date for the week the STARETL process will run.
  3. Code activities using an Activity Code or UDF to identify the adherence grade (A, B, C, D).

    For example, in the sample data, Activity Code 11 (Schedule Adherence Priority) is used.

    Note: Ensure the Activity Code or UDF used is set up correctly both in the Primavera Data Warehouse database and the repository definition.

During T-0 for a given week when you run the STARETL process, the Baseline Planned Finish Date (as of T-0) and the Schedule Freeze Planned Finish Date (as of schedule freeze UDF) for the activities will be captured. You can use these dates along with the assigned adherence grade to calculate the graded schedule adherence in Primavera Analytics.