Configuring P6 EPPM User-Defined Fields for Primavera Data Warehouse

Use the User-Defined Fields screen to choose the available Project, WBS, Activity, Resource, and Resource Assignment user-defined fields (UDFs) to be extracted from P6 EPPM and loaded into Primavera Data Warehouse. Primavera Data Warehouse supports the following user-defined fields data types:

On the User-Defined Fields screen, the Available list box (on the left) shows the available Project, WBS, Activity, Resource, and Resource Assignment UDFs that can be extracted from P6 EPPM and loaded into Primavera Data Warehouse. The Selected list box (on the right) shows the list of selected Project, WBS, Activity, Resource, and Resource Assignment UDFs that have been selected to be extracted from P6 EPPM and loaded into Primavera Data Warehouse. If this is your first time running the Configuration Utility, the Selected list box is empty.

To configure P6 EPPM UDFs for Primavera Data Warehouse, complete the following steps:

  1. In the Available list box, select the UDFs you want to extract.
  2. Click the > button (located between the two list boxes).
  3. Repeat these steps for each UDF you want to extract.
  4. Once you have selected all the required UDFs, click Next.

The Configuration Utility proceeds to the next step. See Finishing the Configuration Utility to continue the configuration process.

Addition Information on UDFs