Purpose
The bar graph and pivot table break projects down by WBS. It shows cost and cumulative values for:
- Actual Cost
- Earned Value
- Planned Value
- Estimate At Completion
Use the expand/collapse control to drill down into the WBS structure.
Location
- On the Home page, click Dashboards.
- Under Primavera, select Project Earned Value.
- On the Project Earned Value dashboard, click the Detailed Earned Value page.
- On the Detailed Earned Value page, expand the Detailed Earned Value by WBS section.
Subject Area
Activity