Resource

Description: The collection of resources that make up the project.

Field

Description

Read-Only

AccrueAt

How cost is accrued against the resource. Values are: 1 = Start, 2 = End, 3 = Prorated, $New4 = Invalid.

No

ActiveDirectoryGUID

The Active Directory GUID for the resource.

No

ActualCost

The actual cost incurred by the resource across all assigned tasks.

No

ActualOvertimeCost

The actual overtime cost incurred incurred by the resource across all assigned tasks.

No

ActualOvertimeWork

The amount of actual overtime work performed by the resource.

No

ActualOvertimeWorkProtected

The duration through which actual overtime work is protected.

No

ActualWork

The amount of actual work performed by the resource.

No

ActualWorkProtected

The duration through which actual work is protected.

No

ACWP

The actual cost of work performed by the resource to the project to-date.

No

AssnOwner

The name of the assignment owner.

No

AssnOwnerGuid

The GUID of the assignment owner.

No

AvailableFrom

The first date that the resource is available.

No

AvailableTo

The last date that the resource is available.

No

BaselineCost

The current cost of the resource in the project baseline.

Yes

BaselineCost1

Baseline Cost 1

No

BaselineCost10

Baseline Cost 10

No

BaselineCost2

Baseline Cost 2

No

BaselineCost3

Baseline Cost 3

No

BaselineCost4

Baseline Cost 4

No

BaselineCost5

Baseline Cost 5

No

BaselineCost6

Baseline Cost 6

No

BaselineCost7

Baseline Cost 7

No

BaselineCost8

Baseline Cost 8

No

BaselineCost9

Baseline Cost 9

No

BaselineFinish

The current finish date of the resource.

Yes

BaselineStart

The current start date of the resource.

Yes

BaselineWork

The current cost of the resource in the project baseline.

Yes

BaselineWork1

Baseline Work 1

No

BaselineWork10

Baseline Work 10

No

BaselineWork2

Baseline Work 2

No

BaselineWork3

Baseline Work 3

No

BaselineWork4

Baseline Work 4

No

BaselineWork5

Baseline Work 5

No

BaselineWork6

Baseline Work 6

No

BaselineWork7

Baseline Work 7

No

BaselineWork8

Baseline Work 8

No

BaselineWork9

Baseline Work 9

No

BCWP

The budgeted cost of work performed by the resource for the project to-date.

No

BCWS

The budget cost of work scheduled for the resource.

No

BookingType

The booking type of the resource. 1 = Committed, 2 = Proposed.

No

CalendarCode

The unique code of the calendar.

No

CalendarUID

The calendar assigned to the resource

No

CanLevel

Whether the resource can be leveled.

No

Code

The code or other information about the resource.

No

Cost

The total project cost for the resource across all assigned tasks.

No

CostPerUse

The cost per use of the resource. This value is as of the current rdate if a rate table exists for the resource.

No

CostVariance

The difference between the cost and baseline cost and the cost.

No

CreationDate

The date that the resource was created.

No

CV

The earned value cost variance through the project status date.

No

EmailAddress

The email address for the resource.

No

Finish

The scheduled finish date of the resource.

No

Group

The unique ID of the parent resource of this resource in the hierarchy.

No

Hyperlink

The title of the hyperlink associated with the resource.

No

HyperlinkAddress

The hyperlink associated with the resource.

No

HyperlinkSubAddress

The document bookmark of the hyperlink associated with the resource.

No

ID

The position identifier of the resource within the list of resources.

No

Initials

The unique identifier of the resource.

No

IsActive

Whether the resource is set to inactive.

No

IsBudget

Whether the resource is a budget resource.

 

IsCostResource

Whether the resource is a cost resource.

 

IsEnterprise

Whether the resource is a enterprise resource.

 

IsGeneric

Whether the resource is generic.

 

IsInactive

Whether the resource is set to inactive.

 

IsNull

Whether the resource is null.

No

MaterialLabel

The unit of measure for the material resource.

No

MaxUnits

The maximum number of units that the resource is available.

No

Name

The name of the resource.

No

Notes

The text notes associated with the resource.

No

NTAccount

The NT account associated with the resource.

No

ObjectId

The unique ID generated by the system.

No

Overallocated

Whether the assignment is overallocated.

No

OvertimeCost

The sum of the actual and remaining overtime cost of the assignment.

No

OvertimeRate

The overtime rate of the resource. This value is as of the current date if a rate table exists for the resource.

No

OvertimeRateFormat

The units used by Microsoft Project to display the overtime rate. 1 = m, 2 = h, 3= d, 4 = w, 5 = mo, 7 = y.

No

OvertimeWork

The amount of overtime work assigned to the resource.

No

ParentObjectId

The unique ID of the parent resource of this resource in the hierarchy.

No

PeakUnits

The largest number of units assigned to the resource at any time.

No

PercentWorkComplete

The percentage of work completed across all tasks.

No

Phonetics

The phonetic spelling of the resource name. For use with Japanese only.

No

RegularWork

The amount of non-overtime work assigned to the resource.

No

RemainingCost

The remaining projected cost of completing the assignment.

No

RemainingOvertimeCost

The remaining projected cost of the resource to complete all assigned tasks.

No

RemainingOvertimeWork

The amount of remaining overtime work required to complete all tasks.

No

RemainingWork

The amount of remaining work required to complete all assigned tasks.

No

StandardRate

The standard rate of the resource. The value is as of the current date if a rate table exists for the resource.

No

StandardRateFormat

The units used by Microsoft Project to display the standard rate. 1 = m, 2 = h, 3= d, 4 = w, 5 = mo, 7 = y, 8 = material resource rate (or blank symbol specified).

No

Start

The scheduled start date of the resource.

No

SV

The earned value schedule variance, through the project status date.

No

Type

The indicator that determines the resource type. 0 = Material, 1 = Work.

No

UID

The unique identifier of the resource.

No

UOMObjectId

The unique ID of the unit of measure that is assigned to the resource.

No

Work

The total work assigned to the resource across all assigned tasks.

No

WorkGroup

The type of workgroup to which the resource belongs. Values are 0 = Default, 1 = None, 2 = Email, 3 = Web.

No

WorkVariance

The difference between the baseline work and the work as minutes x 1000

No