A lean tasks refers to a task that is created using the principles and concepts of lean project management.
To send lean task data from Primavera Cloud to P6 EPPM, you must create a project in Primavera Cloud that includes the following information at a minimum:
- An EPS code associated with the project in Primavera Cloud
- A project name and ID
- One or more activities associated with the project and
- One or multiple tasks to be performed to complete an activity
To send lean task data and project information from Primavera Cloud to P6 EPPM using Primavera Gateway:
- Create tasks and activities for a project in Primavera Cloud.
For more details, see Creating Lean Tasks for a Project in Primavera Cloud.
- Run the synchronization for lean tasks from Primavera Gateway.
For more details, see Running Send Primavera Cloud Project data to P6 for Lean Task Synchronization.