The following project data synchronizations are delivered out-of-the-box to support the delivered business flows for a Unifier - P6 integration in Gateway:
Synchronization | Description |
---|---|
Get Activity Data from P6 | The flow sends activity sheet information from P6 to Unifier, and syncs P6 and Unifier projects. |
Get Activities and Assignments from P6 for EVM | Create/Update Activity sheet in Unifier shells for EVM. |
Send Activity Data to P6 | The flow sends activity data from Unifier to P6. |
Send to Primavera Unifier | The flow sends CBS data (duration summary, expense spread, resource spread) and WBS hierarchy data from P6 to Unifier, and syncs P6 and Unifier projects. |
Update from Primavera Unifier | The flow sends CBS code data from Unifier to P6. |