Preparing Developers for the Upgrade

  1. Back up the development database.

  2. Verify that all developers have checked in their projects and that all projects are unlocked.

  3. Verify that all developers have disconnected from the database. The only open connection must be the account that is performing the upgrade.

  4. Install the new Siebel Tools on development workstations. Keep at least one copy of the previous version of Siebel Tools. You will require it to perform repository operations before the repository merge.

  5. Activate the new Siebel Tools on development workstations. Keep at least one copy of the previous version of Siebel Tools. You will require it to perform repository operations before the repository merge.

  6. Perform all remaining tasks with the new Siebel Tools, unless stated otherwise.