Accept a Tender Package on Behalf of a Subcontractor
When a subcontractor accepts a tender package, it expresses their intention to create and submit a tender. If a subcontractor can't do this in the application, possibly because they prefer to communicate by some other means like email, you can do it for them as long as they have a profile in the application.
Note: You should only accept a tender package on behalf of a tenderer with their knowledge and approval.
To accept a tender package on behalf of a subcontractor:
- Select the Tenders tab to open the All projects page.
- On the All projects page, select a project.
- On the Tender Packages tab, select a tender package.
- On the Tenderers tab, select the checkbox in the row for each tenderer that you want to mark accepted.
- On the Actions menu, select Mark as accepted.
Last Published Friday, February 23, 2024