The Project KPIs column of the Benchmarking page displays the following metrics of your project which can be compared with the corresponding metrics of each benchmark group:
- Predicted Project Delay: The extent of delay predicted for the current project in terms of days.
- Actual Project Delay: The actual delay calculated for the current project in terms of days.
- How many activities are predicted to delay: The activities predicted to be delayed for the project being compared in terms of days and percentages.
- Median predicted delay amount: The median delay calculated for project activities that are predicted to be delayed in terms of days and percentages.
Note: The median is a statistical measure that determines the mid point of a set of values when organized in an ascending or descending order.
In the above example, metrics for the Haitang Corporate Park project are displayed.