The following Key Performance Indicators (KPIs) provide an overall health assessment of a project to predict delay:
- Likelihood of Delay: Indicates how likely it is that a project will be delayed. For example, the likelihood of delay of the Haitang Corporate Park project is 68%.
- Delay amount: This tile describes the extent of project delay in number of days. For example, the Haitang Corporate Park project is predicted to be delayed by 197 days.
- Activities with Delay: This tile reflects the number of activities within the project that are contributing to project delay. For example, the number of Activities with Delay predicted in the Haitang Corporate Park is 10.
- Schedule assessment: This tile identifies the number of activities in the underlying schedule that do not conform to schedule parameters set by your organization. For example, the number of non-conforming activities in the Schedule Assessment of the Haitang Corporate Park project is 32.
Using the information from all the KPIs, the following insight can be drawn for the Haitang Corporate Park project: This project has a 68% chance of being delayed by 197 days with 10 activities responsible for the delay. Moreover, the underlying project schedule has 48 activities that may have some planning issues.
Select any KPI to review details of a specific project.
Note: Construction Intelligence Cloud is delivered with predetermined thresholds that determine the color of each KPI or metric. These threshold settings are specified in the administration application of Construction Intelligence Cloud which can also be modified according to the needs of your organization. To change the value or range of thresholds for Likelihood of Delay, Activities with Delay, or Schedule assessment, contact your Construction Intelligence Cloud administrator.