Workflows Predicted to Delay Section
The following information is displayed for each workflow:
- Workflow No.: The unique identification number for each workflow in the source application.
- Workflow title: The name of the workflow in the source application.
- Docs: The total number of documents in the workflow. For example, a total of 5 documents are included in the workflow.
- Predicted to delay docs: The number of documents predicted to be delayed in the workflow. For example, 2 documents are predicted of be delayed out of a total of 5.
- Planned finish date: The workflow completion date when it was initiated, based on the days assigned to each step and the working week set for the project.
- Estimated finish date: The expected workflow completion date on that day. It accounts for step progress and considers overdue or early completion to recalculate the final workflow completion.
- Predicted finish date: The date on which the workflow is predicted to complete, using the number of days calculated for Predicted delay.
- Predicted delay: The number of days that the workflow is predicted to be delayed from the planned finish date by CIC Advisor.
For example, if the planned finish date for a document is 01-Feb, 2023, and the predicted delay is 6 days, then the workflow will be completed on 07-Feb-2023.
- Actions: Select any of the following options:
- Click Workflow to view the predicted risk of delay for each workflow step.
- Click Action to view the selected workflow in Aconex.
Related Topics
Filters Pane of Review Delay Risk Page
Last Published Thursday, December 7, 2023