To make changes to status updates:
- Click Approvals.
- On the Approvals navigation bar, select Status Updates.
- On the Status Updates page:
- Select Override.
- In the Override Updates for Activity dialog box:
- Enter new values for the fields you want to override.
- Select the Notify team member by email option if you want the team member to receive an email about the rejected status update.
- Select Override
Note: If you select to override values in an activity update and a team member later updates those values by resubmitting a status update, the values you enter here will be lost.
Tips
- Pending updates for a project checked out in P6 Professional or opened exclusively are not displayed until the project is checked in or the exclusive lock is released.