Configure activity issues to account for changes since the last update on the issue.
To configure activity issues:
- Click Projects.
- On the Projects navigation bar, click Activities.
- On the Activities page, select an activity and click the Issues detail window.
Note: To configure a project or WBS issue, select a project or WBS in place of an activity.
- In the Issues detail window:
- Select an issue.
- Select an option or enter a value for each field.