Configuring Activity Relationships

Configure activity relationships to adjust interdependencies between different activities.

To configure activity relationships:

  1. Click Projects.
  2. On the Projects navigation bar, click Activities.
  3. On the Activities page:
    1. Click Gantt View.
    2. Click Gantt Settings and select to show relationships.
    3. Right click the relationship line of the relationship you want to configure and click Edit Relationship.
      • In the Edit Relationship dialog box, configure the type and lag and click Apply.
    4. On the Activities page, click Save.

Tips

You can also configure predecessor and successor relationships from the Predecessor, Successor, or Relationships detail windows.

Related Topics

About Relationships

About Relationship Lines

Creating Activity Relationships

Assigning Predecessor Relationships

Configuring Predecessor Relationships

Assigning Successor Relationships

Configuring Successor Relationships

Configuring Predecessor Relationships

Configuring Successor Relationships