Approving or Denying Budget Change Requests

If you have the authority, you can approve or deny a budget change request for a WBS, project, or entire EPS element.

To approve or deny a budget change request:

  1. Click Projects.
  2. On the Projects navigation bar, click EPS.
  3. On the EPS page, select the EPS or project with a budget change request and click the Budget Log detail window.
  4. In the Budget Log detail window:
    1. Select and review the budget change request.
    2. In the Status list, select Approved or Not Approved.
    3. In the Reason field, enter an explanation for the new status.
    4. Save your changes.

Tips

Related Topics

About Budgets

Working with Budgets

Establishing Budgets

Creating Budget Change Requests



Legal Notices | Your Privacy Rights
Copyright © 1999, 2021

Last Published Monday, December 6, 2021