Create activities to define a more detailed breakdown of projects or WBSs.
To create activities:
- Click Projects.
- On the Projects navigation bar, click Activities.
- On the Activities page:
- Click the Row Actions menu and select Add Activity.
- Enter an ID in the ID/Code field.
Note: The ID/code must be unique in the project.
- Enter a name in the Name field.
- Click Save.
Tips
- Right-click a project, WBS, or activity and select Add Activity to quickly add an activity.You can also right click in the background of the Gantt view and select Add Activity.
- The application automatically names new activities New Activity.
- The default limit allows you to create up to 5000 activities per activity view.