Create baselines to measure project performance.
To create a baseline:
- Click Projects.
- On the Projects navigation bar, click Activities or EPS.
- On the Activities or EPS page
- Click the Actions menu and select Define Baselines....
- In the Define Baselines dialog box:
- Select the project to which you will add the baseline.
- Click Row Actions and select Add.
- Enter a name in the Baseline Name field.
- Select a type from the Baseline Type list.
- Click Save.
Tips
- The application automatically assigns the baseline a name based on the selected project. For example, if you select
Project A
, the application will name the newly created baselineA - B1
. - Specify the default Project Baseline and User's Primary Baseline by selecting from the list of available baselines for each project in the table on the Baselines dialog box.
- Click Convert a Project to Baseline and select a project to convert a project into a baseline.
- Select a baseline and click Restore a Baseline to remove the baseline and make it a project.
- When you create a new baseline, the Publish option is switched off by default.