You can set rate information for resources or roles.
To specify resource assignment rates:
- Click Projects.
- On the Projects navigation bar, click Activities.
- On the Activities page, select an activity in the table and click the Assignments detail window.
- In the Assignments detail window:
- Add the Rate Type and Rate Source columns.
- Select an option for the type and source.
- Save your changes.
Tips
When you save your changes, costs for the assignment are recalculated based on the new rate: Cost equals Units times Price/Unit. You can add the Price/Unit column to the detail window to view the price used. To manually specify a price/unit, select Override in the Rate Source field and type a value in the Price/Unit field.