- Choose Project, Assign Baselines.
- In the Project field, select the project to which you want to assign baselines.
- In the Secondary and Tertiary fields, select an existing baseline of the current project.
Note: The Current Project is automatically used as the Primary baseline; thus, it does not have to be set.