- Choose Enterprise, Resource Codes.
- Click Modify.
- Click Add, then type the name of the resource code.
- In the Max Length field, specify the maximum number of characters for the resource code's values.
- Click Close.
Note
- If you intend to use Oracle Analytics Publisher (formerly BI Publisher), avoid using commas when creating data other than Project names. The way that data other than Project names is passed to BI Publisher can cause a comma to be interpreted as a delimiter between data items.
Tip
- To change the order in which resource codes are listed, select the resource code you want to move in the Resource Code Definitions dialog box, then click Shift Up or Shift Down.