- Choose Project, Activities.
- Select the activity whose float values you want to view.
- Display Activity Details, then click the Status tab.
The Free Float field displays the amount of time the selected activity can be delayed without delaying the activities that immediately follow (successor activities).
The Total Float field displays the amount of time the selected activity can be delayed without delaying the project's finish date.
Tip
- You can also display Total Float and Free Float columns in the Activity Table.
Note
- An activity's free and total float is automatically calculated each time you schedule the project. You cannot edit an activity's float values directly.
Define Activity Table columns
Display window details