Actual Cost

Actual Cost is the actual total cost incurred on the activity as of the project data date. Computed as Actual Cost = Actual Labor Cost + Actual Nonlabor Cost + Actual Material Cost + Actual Expense Cost. Actual Cost is the same as the Actual Total Cost.



Legal Notices | Your Privacy Rights
Copyright © 1999, 2021

Last Published Monday, December 6, 2021