Calculations tab - Project Details

Use this tab to specify how to calculate cost and estimate resource use when you update activities in the selected project.

Activities

Default Price/Unit for activities without resource or role Price/Units: The project’s default cost of work for activities with no resources or roles. Activities may have labor/ nonlabor units with no assigned resources/roles or resources/roles that do not have prices. In such cases, this setting is used to calculate the cost for activities. To change the default price, type a new amount, followed by a forward slash (/) and time unit.

Activity percent complete based on activity steps: Mark to base percent complete on activity steps when using the physical percent complete type.

Link Planned or Budget and At Completion for not started activities: When this option is checked, Budgeted or Planned, Remaining, and At Completion values are set to equal for not started activities. If you want to baseline, or hold constant, the Budgeted or Planned values in your project plan while recording updates to Remaining or At Completion values, unmark the checkbox to turn off this option. When this option is off, Budgeted or Planned values for a Not Started activity are retained when you update its Remaining or At Completion values.

Notes

Reset Planned or Original Duration and Units to Remaining: Choose this option to recalculate the Planned duration and dates based on the At Completion duration and Remaining dates and recalculate Planned units based on the At Completion units for activities and assignments. If an activity does not have actual costs, the Planned Cost, At Completion Cost, and Estimate to Complete are equal.

Reset Remaining Duration and Units to Planned or Original: Choose this option to recalculate the At Completion duration and Remaining dates based on the Planned duration and dates, and recalculate At Completion units based on the Planned units on activities and assignments. If an activity does not have actual costs, the Planned Cost, At Completion Cost, and Estimate to Complete are equal.

Resource Assignments

When updating Actual Units or Cost

Add Actual to Remaining: Choose to calculate a new At Complete as the sum of the actual and remaining units or costs.

At Complete = Actual (units or costs) + Remaining (units or costs)

When working with a cost-plus contract, use this option to determine the true At Complete. Actual units and costs are normally calculated using this option.

Subtract Actual from At Completion: Choose to calculate the remaining units or costs as the difference between the At Complete and Actual units or costs.

Remaining (units or costs) = At complete (units or costs) - Actual (units or costs)

When working with a fixed-price contract that must be accomplished within a fixed budget, use this option. This approach tracks the amount remaining before you exceed the budget.

Recalculate Actual Units and Cost when duration % complete changes: Mark to estimate actual units and costs as

Actual (units or costs) = budgeted or planned (units or costs) * Duration % Complete

If an activity does not have any resource assignments, Actual units or costs are calculated using the activity's budgeted or planned units or costs.

P6 Professional performs these calculations whenever you update the Duration % complete.

Values you specify override the module's calculated values. If you do not mark the checkbox, the module does not estimate actuals and the actual fields remain blank unless you specify values.

Notes

When connected to a P6 EPPM database: You must have the appropriate project privilege as defined in P6 to enable this option.

Update units when costs change on resource assignments: Mark this checkbox for P6 Professional to recalculate units when costs are updated for the assignment. Cost changes, such as modifying the remaining cost for activities, cause P6 Professional to recalculate units.

Link actual to date and actual this period units and costs: Mark this checkbox for P6 Professional to recalculate actual or actual this period units and costs when one of these values is updated. P6 Professional marks this option by default. This option must be marked if you plan to store period performance or edit past period actuals for a project.